TENDER FOR TO HIRE SERVICE OF GEOTECHNICAL INVESTIGATION SERVICES

 Ngali Mining Ltd is a subsidiary of Ngali Holdings based in Kigali in BODIFA MERCY HOUSE KIMIHURURA IN 7TH FLOOR. We are inviting you to compete for this tender according to the technical specifications

Tender No: 03/7/NM/2020 for the service of drilling and geotechnical investigation services

TERMS OF REFERENCE FOR DRILLING AND GEOTECHNICAL INVESTIGATION SERVICES

Introduction

Ngali Mining Ltd is looking for a competent company to conduct drilling works and geotechnical tests at the proposed dam site of the Rusizi III Power Plant on the Rwandan side of the Rusizi riverbanks, in Rusizi District.

Scope of the Work

The objective of this investigation program is to gain reliable data about the geological and geotechnical conditions of the project and about the variability and quality of the construction material in the vicinity of the site.

The Services shall be carried out in accordance with the following standards:

  • BS/AASHTO standard
  • ISRM: Suggested methods for rock characterization, testing, and monitoring (site characterization, laboratory testing of rock samples, in-situ stress measurements, geophysical testing),
  • Eurocode 7, Part 2 (Ground investigations),

In addition, the Drilling Contractor shall apply internationally accepted best practices and technical specifications in order to maximize the reliability of the collected data.

The following table shows the location and details of the drilling works.

Original Dam Site

BH

Location

X

Y

Z

Depth

Azimuth

Remark

BH-13

Dam Axis LB

716,302

9,702,467

1,103

40

Vertical

BH-14

Extension Dam Axis LB

716,285

9,702,515

1,125

30

Vertical

BH-16

Water Intake Mid Slope

716,245

9,702,485

1,107

30

Vertical

BH-17

Water Intake River Bank

716,235

9,702,445

1,095

40

Vertical

Alternative Dam Site

BH-3N

Dam Axis LB

715,887

9,702,446

1,128

50

N 65

BH-4N

Water Intake

715,844

9,702,653

1,145

30

Vertical

BH-8N

Ridge Spillway Chute

715,938

9,702,535

1,165

60

Vertical

Total

280

m

In-Situ Tests

  • Water pressure Lugeon Test
  • Standpipe Piezometer
  • SPT at Dam sites

Laboratory Testing

  • Determination of density and absorption (surface samples)
  • Determination of density and absorption (surface samples)
  • Uniaxial Compressive Test with modulus of elasticity (dry)
  • Uniaxial Compressive Test with modulus of elasticity soak 72hrs
  • Point load test
  • shear strength of discontinuity
  • splitting tensile strength in rock samples (ASTMD 3967)

Ngali Mining will provide the following:

  • Accessibility from the low bed truck last point to the site and the mobility between the drilling sites.
  • Drilling water supply

Daily Reporting requirements

Drilling daily record sheets shall be prepared and submitted the following day. The format of the drilling record sheet shall be agreed with the Engineer prior to the works. The sheets shall include but not be limited to:

  • Name of Project, Client and Drilling Contractor
  • Borehole number
  • Day and date
  • Weather conditions
  • Borehole orientation is given as an angle of the hole to the horizontal and compass bearing, if not vertical
  • Drilling rig type and method of drilling
  • Type of core bit and barrel, and diameter of core, or other drilling tools
  • Drilling flush type, estimated percentage returns, and colour (if used)
  • Hole and cashing depths and diameter
  • Groundwater level measured by electric dip meter at the start and end of each day. The groundwater level measurements shall continue until the Drilling Contractor demobilizes from the Site.
  • Depth of any water strike together with the rise in water level 20 minutes after the strike without further drilling
  • Top and bottom depth of each core run (if used)
  • Total core recovery as a percentage for each core run (if used)
  • Top and bottom depth of each in-situ test, the test type, and test result
  • Top and bottom depth and a brief description of each stratum encountered
  • Details of backfilling, grouting, and/or piezometer installation

Reports

The Drilling Contractor shall submit the following during the course of the fieldwork:

  • Daily drillers record sheets
  • The electronic version of drillers record sheet typed into a Pro-forma spreadsheet provided by the Engineer, format compatible with MS Excel
  • Copies of preliminary test results sheets within 24 hours of the test to which they relate
  • Core photographs for approval
  • Topographic maps in requested scale
  • Geological-Geotechnical Investigation Report
  • All reports shall be in the English and French languages.

Contractor’s proposal

The contract’s proposal has to cover the following sections and the marking scheme will be 100% whereas the pass mark is 50% for technical evaluation and 30% financial evaluation with a pass mark of 20%

Submitted By Ngali Mining Ltd, July 2020

Drilling Contractor’s Methodology 20%

  1. Time Schedule for Services and early completion date 20%
  2. Experience is 10%
  3. Financial offer is 50% and the pass mark is 35%

Cost Estimates as per the following table:

Price (USD) Breakdown Table

Item

Description

Unit

Qty

 Unit Rate

 Amount

 Remarks

Drilling Works

1

Vertical Drilling (0-30)

m

210

2

Vertical Drilling (30-50)

m

60

3

Vertical Drilling (50-180)

m

10

4

Inclined Drilling (30-45 deg) (0-50)

m

0

for records

5

Inclined Drilling (30-45 deg) (>50)

m

0

for records

6

Inclined Drilling (< 30 deg) (0-50)

m

0

for records

7

Inclined Drilling (< 30 deg) (> 50)

m

0

for records

8

Drilling in Soil

m

0

for records

Sub/Total – Drilling Works

280

In-Situ Tests

1

Water pressure Lugeon Test

No

 78

Number of tests are just indicative and subjected to change due to ground condition

2

Standpipe Piezometer

m

90

3

SPT at Damsites

No

21

Sub/Total – In Situ Tests

Laboratory Testing

E1

Determination of density and absorption (surface samples)

ea

10

Number of tests are just indicative and subjected to change due to ground condition.

E2

Determination of density and absorption (surface samples)

ea

10

E3

Uniaxial Compressive Test with modulus of elasticity (dry)

ea

6

E4

Uniaxial Compressive Test with modulus of elasticity soak 72hrs)

ea

6

E5

Point load test

ea

21

E6

shear strength of discontinuity

ea

3

E7

splitting tensile strength in rock samples (ASTMD 3967)

ea

7

Sub/Total – Laboratory Testing

  1. Drilling Contractor’s Personnel and Personnel Schedule as per the following table:

S.no

Position

Name

Years of experience (general)

Years of experience in the proposed position

1

2

3

4

5

6

7

 

Interested bidders should submit the bid offers to the procurement office of Ngali Mining at BODIFA MERCY HOUSE KIMIHURURA RUGANDO on the 7th floor. The deadline for submitting bids will be on 3rd August 2020 at 10 am. The opening of the envelopes will be the same day at 11 am in the Boardroom for Ngali Mining Ltd.

Done Kigali on 29th July 2020

tender for drilling equipment SPT standard penetration test kit9e0d4816bc4c0bdb51c89a02581a8371

 





CLICK HERE TO JOIN MUCURUZI.COM WHATSAPP BUSINESS GROUP





Kindly Note

All Jobs and Opportunities Published on mucuruzi.com are completely free to apply. A candidate should never pay any fee during the recruitment Process. Even if mucuruzi.com does its best to avoid any scam job or opportunity offer, a job seeker or an opportunity seeker is 100% responsible of applying at his own risk.
Check well before applying, if you doubt about the eligibility of any offer do not apply and notifie to mucuruzi.com via this email: mucuruzi2016@gmail.com and remember to never pay any fee to have a job or get any opportunity, if you do so, do it at your own risk.








WELCOME TO OUR WHATSAPP GROUP

Related posts

Leave a Reply